Construction Calculator
Interactive estimation tool

Concrete Slab Calculator for Cement, Sand and Aggregate

Calculate concrete slab volume, dry mix, cement bags, sand, aggregate and waste allowance for construction material estimates.

Estimation Inputs

Enter measurements in the selected display units. The calculator converts them to canonical formula units before running the estimate.
m²

Surface area of the slab.

m

Concrete pour thickness.

parts

Cement proportion in the mix.

parts

Sand proportion in the mix.

parts

Aggregate proportion in the mix.

coef

Compaction and shrinkage factor.

%

Allowance for spill and site loss.

kg

Weight of one cement bag.

Pricing & Rates

Prices are editable per estimate. Regional settings only provide starting rates, tax and currency labels.
AED

Price per purchase unit used by this calculator.

AED

Applied to the estimated purchase quantity.

%

Use 0 if tax is not applicable.

Quantity Takeoff

wet Volume

10

total Wet Volume

10.5

dry Volume

16.17

cement Volume

2.31

Formula Trace

Slab Wet Volume:

Area * Thickness

100.00 m² * 0.100 m

= 10.000 m³

Wet Volume (with Waste):

Wet Volume * (1 + Wastage % / 100)

10.00 m³ * (1 + 5.0 / 100)

= 10.500 m³

Dry Mix Volume Required:

Wet Volume (with Waste) * Dry Volume Factor

10.50 m³ * 1.54

= 16.170 m³

Cement Dry Volume:

Dry Volume * (Cement Ratio / Ratio Sum)

16.17 m³ * (1 / 7)

= 2.310 m³

Cement Bags (50kg bags):

ceil((Cement Volume * Density 1440 kg/m³) / Bag Weight)

ceil((2.310 m³ * 1440) / 50 kg)

= 67.000 bags

Sand Dry Volume:

Dry Volume * (Sand Ratio / Ratio Sum)

16.17 m³ * (2 / 7)

= 4.620 m³

Coarse Aggregate Volume:

Dry Volume * (Aggregate Ratio / Ratio Sum)

16.17 m³ * (4 / 7)

= 9.240 m³

Estimate Outcome

3D Concrete Slab DiagramSlab Volume Model
Material Cost:6700.00 AED
Labor Cost:8040.00 AED
Tax VAT:737.00 AED
Total Price:15477.00 AED
Create a project and room first, then return here to attach this estimate to the BOQ.

Calculation guide and formulas

Use this concrete slab calculator to estimate wet volume, dry concrete mix volume, cement bags, sand and aggregate for slabs, footings and small pours.

Understand the units, allowances and purchase rounding (English).

Wet Volume = Area × Thickness; Dry Volume = Wet Volume × Dry Volume Factor

Worked example

A 100 m² slab with 0.1 m thickness needs 10 m³ wet concrete. With 5% waste and a 1.54 dry factor, dry volume is 16.17 m³. For a 1:2:4 mix, cement is about 2.31 m³ or 67 bags.

Frequently asked questions

  • Q: Why use a dry volume factor for concrete?

    A: Dry ingredients contain voids. A dry volume factor accounts for compaction and shrinkage when cement, sand, aggregate and water are mixed.

  • Q: Can this concrete calculator replace structural design?

    A: No. It is for material estimation and planning. Structural grade, reinforcement and code requirements should be checked by a qualified professional.